Project Duration
Stipulated Date of Commencement October 26 2006
Stipulated Date of Completion /
Likely Date of Completion
February 25 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 15,119,623.00
Awarded for ₹ 11,376,000.00