Project Duration
Stipulated Date of Commencement January 05 2008
Actual Date of Completion October 30 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 72,165,175.00
Awarded for ₹ 93,964,789.50

Project highlights

The project includes : – Construction of a Multipurpose Hall, Construction of a Swimming Pool and Development of Football ground
Multipurpose Hall
Total floor area is 1053 sq. mts. in two floors, the Ground floor is designed to accommodate 2 – Badminton courts with special flooring made up of “Teak Wood – Zyrex”. There is a stage provided to conduct small public functions and local cultural events. On the first floor, provision is made for Gymnasium and also a viewing gallery and other utilities
Swimming Pool
The swimming pool is of size 21 m x 25 m, smaller than the size of a pool used in Olympics games. The depth of the pool varies from 3.00 m at the deep end to 1.09 m at the shallow end. A baby pool is also provided along side. Standard filtration equipment with Ionisation System is provided for operation and maintenance of Swimming Pool
FOOTBALL GROUND
Football ground is developed over an area of 80 m x 60 m with exclusive players’ area, viewers gallery and adequate toilet facilities.