Project Duration
Stipulated Date of Commencement
July 08 2008
Stipulated Date of Completion /
Likely Date of Completion October 07 2009
Likely Date of Completion October 07 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 149,211,856.00
Awarded for
₹ 191,699,335.00
Project highlights
Road widening and hotmixing of internal and main roads, construction of drains with precast RCC covers, Footpath with pavers etc. Constructio of seating on foopath along the main road. Renovation of Muncipality Office, construction of compound walls etc.