Project Duration
Stipulated Date of Commencement
April 23 2012
Stipulated Date of Completion /
Likely Date of Completion May 22 2013
Likely Date of Completion May 22 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,62,97,694.73
Awarded for
₹ 7,06,63,484.94
Project highlights
The total area of the plot is 22205.00 sq.m
The building is a G+1 structure. The total floor area is 3400 sqm.
The ground floor comprises of a Canteen with kitchen, store rooms, Electrical room, room for Library/Internet, Conference room, a room for Food Inspector & Local Authority along with a store, PFA Cell with store, room for Accounts Department with store, Chemical Store and toilet for ladies & gents.
* The first floor comprises of Pharmacist room, store rooms, Cabins for Director, Dy. Director, Administration room, Asst. Drug Controller room, ladies and gents toilet
* Total parking space provided is for 65 vehicles.