Project Duration
Stipulated Date of Commencement December 14 2012
Stipulated Date of Completion /
Likely Date of Completion
January 12 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 823,021.00
Awarded for ₹ 926,207.80

Project highlights

Compound wall