Project Duration
Stipulated Date of Commencement
July 07 2011
Stipulated Date of Completion /
Likely Date of Completion August 05 2011
Likely Date of Completion August 05 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 402,850.00
Awarded for
₹ 407,375.00
Project highlights
Solar water heating system for bathrooms