Project Duration
Stipulated Date of Commencement
March 07 2019
Stipulated Date of Completion /
Likely Date of Completion March 06 2020
Likely Date of Completion March 06 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 21,580,100.00
Awarded for
₹ 21,693,694.46
Project highlights
Ground floor:
1) Covered Parking facility for around 63 cars.
2) Modern toilet blocks with adequate facilities to maintain hygiene.
First floor:
3) Multipurpose Hall for activities like meetings, gathering, cultural programs etc.
4) Hall having capacity of around 752 seats..
5) Modern toilet blocks with adequate facilities to maintain hygiene.
6) Hall has stage with two changing rooms on both sides.
7) False ceiling with ceiling lights for better appearance and lighting.
8) Covering first floor with double skin roofing with steel framework.
9) Covering ground floor chajja with decorative Manglore tiles.
Landscaping:
10) Surrounding area is provided with pavers .