Project Duration
Stipulated Date of Commencement
September 22 2017
Stipulated Date of Completion /
Likely Date of Completion September 21 2020
Likely Date of Completion September 21 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,714,108.00
Awarded for
₹ 6,196,686.00
Project highlights
Maintenance of landscaping works at Goa Medical College.