Project Duration
Stipulated Date of Commencement November 07 2017
Stipulated Date of Completion /
Likely Date of Completion
November 25 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 827,427.00
Awarded for ₹ 848,095.00

Project highlights

The scope of work includes replacement of non-functional CFL light fixtures with the LED light fixtures, LED street light fixtures, repairs of street lights in the courtyard of ESG premises.