Project Duration
Stipulated Date of Commencement
August 29 2017
Stipulated Date of Completion /
Likely Date of Completion August 28 2017
Likely Date of Completion August 28 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,000,000.00
Awarded for
₹ 5,000,000.00
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.